Development plan
Phase of
construction
|
Total area,
thousands of
sq.m |
Phase start |
Term of delivery |
| 1st Phase |
102.4 |
Q3 2006 |
Set in operation |
| 114.5 |
Q3 2006 |
Q4 2009 |
| 2nd Phase |
151.1 |
2010 |
2012 |
| 3rd Phase |
197.3 |
2010 |
2012 |
| 4th Phase |
211.3 |
2011 |
2013 |
| 5th Phase |
105.3 |
2011 |
2013 |
| TOTAL |
881.9 |
|
| 1st Phase |
- 6 office buildings, total area 169 039 sq.m.
- multilevel parking, 1 478 parking spots
- catering
- restaurant a la carte
- bank department
- conference hall for 250 seats
- retail zone
- data center of 2nd level for 55 slots
|
| 2nd Phase |
- 2 office buildings, total area 99 040 sq.m.
- business hotel*** , 250 rooms
- multilevel parking, 993 parking spots
- automatic parking
- catering
- data center of 3rd level for 250 slots
- retail zone, area 14 800 sq.m.
|
| 3rd Phase |
- 2 office buildings, total area 128 010 sq.m.
- multilevel parking, 1510 parking spots
- catering
- large retail zone
|
| 4th Phase |
- office buildings, total area 169 570 sq.m.
- multilevel parking, 1523 parking spots
- catering
- large retail zone
|
| 5th Phase |
- office buildings, total area 27 940 sq.m.
- multilevel parking, 1 002 parking spots
- business hotel*** , 200 rooms
- catering
- conference hall
- large retail zone
|
|
|
|
|